Earned value management (EVM), earned value project management, or earned value performance management (EVPM) is a project management technique for measuring project performance and progress in an objective manner.

Earned value management (EVM), earned value project management, or earned value performance management (EVPM) is a project management technique for measuring project performance and progress in an objective manner. \begin{align} \mathrm{EV} & = \sum_\mathrm{Start}^\mathrm{Current} \mathrm{PV(Completed)} \quad \mathrm{or} \quad \mathrm{EV} = \mathrm{budget\, at\, Completion\,(BAC)} \times \mathrm{Actual\%\, Complete} \end{align} EV is calculated by multiplying %complete of each task (completed or in progress) by its planned value Figure 2 shows the EV curve (in green) along with the PV curve from Figure 1. The chart indicates that technical performance (i.e. progress) started more rapidly than planned, but slowed significantly and fell behind schedule at week 7 and 8. This chart illustrates the schedule performance aspect of EVM. It is complementary to critical path or critical chain schedule management. Figure 3 shows the same EV curve (green) with the actual cost data from Figure 1 (in red). It can be seen that the project was actually under budget, relative to the amount of work accomplished, since the start of the project. This is a much better conclusion than might be derived from Figure 1. Figure 4 shows all three curves together – which is a typical EVM line chart. The best way to read these three-line charts is to identify the EV curve first, then compare it to PV (for schedule performance) and AC (for cost performance). It can be seen from this illustration that a true understanding of cost performance and schedule performance relies first on measuring technical performance objectively. This is the foundational principle of EVM. CV = EV - AC \end{align} CV greater than 0 is good (under budget). CPI = {EV\over AC} \end{align} CPI greater than 1 is favorable (under budget). CPI that is less than 1 means that the cost of completing the work is higher than planned (bad). When CPI is equal to 1, it means that the cost of completing the work is right on plan (good). CPI greater than 1 means that the cost of completing the work is less than planned (good or sometimes bad). Having a CPI that is very high (in some cases, very high is only 1.2) may mean that the plan was too conservative, and thus a very high number may in fact not be good, as the CPI is being measured against a poor baseline. Management or the customer may be upset with the planners as an overly conservative baseline ties up available funds for other purposes, and the baseline is also used for manpower planning. EAC = AC + {(BAC-EV)\over CPI} = {BAC \over CPI} \end{align} This formula is based on the assumption, that the performance of the project (or rather a deviation of the actual performance from a baseline) to date gives a good indication of what a performance (or rather deviation of a performance from a baseline) will be in the future. In other words, this formula is using statistics of the project to date to predict future results. Therefore, it has to be used carefully, when the nature of the project in the future is likely to be different from the one to date (e.g. performance of the project compare to baseline at the design phase may not be a good indication of what it will be during a construction phase). While algebraically, ETC = EAC-AC is correct, ETC should never be computed using either EAC or AC. In the following equation: \begin{align} EAC = AC + ETC \end{align} ETC is the independent variable, EAC is the dependent variable, and AC is fixed based on expenditures to date. ETC should always be reported truthfully to reflect the project team estimate to complete the outstanding work. If ETC pushes EAC to exceed BAC, then project management skills are employed to either recommend performance improvements or scope change, but never force ETC to give the "correct" answer so that EAC=BAC. Managing project activities to keep the project within budget is a human factors activity, not a mathematical function. TCPI_{BAC} = { BAC - EV \over BAC - AC } or for the TCPI based on EAC (describing the performance required to meet a new, revised budget total EAC): TCPI_{EAC} = { BAC - EV \over EAC - AC } This implies, that if revised budget (EAC) is calculated using Earned Value methodology formula (BAC/CPI), then at the moment, when TCPI based on EAC is first time calculated, it will always be equal to CPI of a project at that moment. This happens because when EAC is calculated using formula BAC/CPI it is assumed, that cost performance of the remaining part of the project will be the same as the cost performance of the project to date. The graph illustrates three scenarios outlined in PMI's "Process Group: A Practice Guide" (2022 edition, p. 311): The To-Complete Performance Index (TCPI) required to complete the project on plan, assuming the Budget at Completion (BAC) remains unchanged (i.e., EAC = BAC). The Estimated At Completion (EAC) calculated under the assumption that the Cost Performance Index (CPI) remains constant (i.e., TCPI = CPI). The EAC calculated under the assumption that future work will be accomplished at the planned rate (i.e., TCPI = 1). IEAC = \sum AC + { \left( BAC - \sum EV \right) \over CPI }

Sources

Defense Contract Management Agency (2006) "Earned Value Implementation Guide" DAU link GAO (2009) "GAO Cost Estimating and Assessment Guide" GAO-09-SSP Bembers, Ivan, Ed Knox, Michelle Jones and Jeff Traczyk (Jan 2017). "EVM System's High Cost, Fact or Fiction?" Defense AT&L Magazine. https://www.dau.mil/library/defense-atl/_layouts/15/WopiFrame.aspx?sourcedoc=/library/defense-atl/DATLFiles/Jan-Feb2017/Bembers_Knox_Jones_Traczyk.pdf Wagner, Bernhard (2020-11-01) "Earned Value Management (EVM) to control software development" Measuring Integrated Progress on Agile Software Development Projects Monitoring Scrum Projects with Agile EVM and Earned Business Value (EBV) Metrics UK MoD on-line training using Flash player U.S. DoD DAU Acquisition Community Earned Value Management website U.S. Defense Contract Management Agency Guidebook EVM earned value management general definitions EVMS Surveillance Instruction, U.S. Defense Contract Management Agency

Text derived from https://en.wikipedia.org/w/index.php?oldid=1367546529 under CC BY-SA 4.0; modifications have been made.

Sources cited in this revision

17 named source(s) extracted from the cited revision. A source with no author is shown by its publication; nothing is invented.