In inventory management, Economic Batch Quantity (EBQ), also known as Optimum Batch Quantity (OBQ) is a measure used to determine the quantity of units that can be produced at the minimum average costs in a given batch or product run. EBQ is basically a refinement of the economic order quantity (EOQ) model to take into account circumstances in which the goods are produced in batches. The goal of calculating EBQ is that the product is produced in the required quantity and required quality at the lowest cost. The EOQ model was developed by Ford W. Harris in 1913, but R. H. Wilson, a consultant who applied it extensively, and K. Andler are given credit for their in-depth analysis. Aggterleky described the optimal planning planes and the meaning of under and over planning, and the influence of the reduction of total cost. Wiendahl used Harris and Andler's equation for the determination of the optimal quantity. Härdler took into account the costs of storage and delivery in determining the optimal batch quantity (EBQ). Muller and Piasecki asserted that inventory management is explained only with the basics of an optimal quantity calculation.
In inventory management, Economic Batch Quantity (EBQ), also known as Optimum Batch Quantity (OBQ) is a measure used to determine the quantity of units that can be produced at the minimum average costs in a given batch or product run. EBQ is basically a refinement of the economic order quantity (EOQ) model to take into account circumstances in which the goods are produced in batches. The goal of calculating EBQ is that the product is produced in the required quantity and required quality at the lowest cost. The EOQ model was developed by Ford W. Harris in 1913, but R. H. Wilson, a consultant who applied it extensively, and K. Andler are given credit for their in-depth analysis. Aggterleky described the optimal planning planes and the meaning of under and over planning, and the influence of the reduction of total cost. Wiendahl used Harris and Andler's equation for the determination of the optimal quantity. Härdler took into account the costs of storage and delivery in determining the optimal batch quantity (EBQ). Muller and Piasecki asserted that inventory management is explained only with the basics of an optimal quantity calculation. \text{Maximum Inventory Level}=Q-\frac{Q d}{p}=Q(1-\frac{d}{p}) \text{Average Inventory}=\frac{1}{2}\bigg[Q(1-\frac{d}{p})\bigg]=\frac{Q}{2}\bigg(1-\frac{d}{p}\bigg) \text{Total carrying cost}=\frac{C_CQ}{2}\bigg(1-\frac{d}{p}\bigg) In this case the ordering cost, C_O is often the setup cost for production. \therefore \text{Total cost TC} = \bigg(\frac{C_O D}{Q}\bigg) + \bigg[\frac{C_C Q}{2}(1-\frac{d}{p})\bigg] The EBQ is calculated as the point where the total cost is minimum as follows: \text{For TC to be minimum,}{dT \over dQ}=0. \therefore Q = \sqrt{ \frac{ 2 \cdot C_O \cdot D }{ C_C \bigg(1-\frac{d}{p}\bigg) } } Where C_O is the cost of setting up a batch, D is the annual demand, d is the daily rate at which inventory is demanded, C_C is the inventory holding cost per unit per annum, and p is the rate of production per annum. Compared to the EOQ equation, there is a factor d/p introduced. This is due to the fact that when we produce a component while it is used in downstream production at the same time, inventory levels will not reach the same peak as when we order the components from a supplier and receive the batch at a single point in time. For instance, if we produce two different components (with the same processing time) intermittently then d/p is 0.5. It is evident from this equation that the economic batch quantity increases as the annual requirements or the preparation and setup costs increase that is, they are (not directly) proportional to each other. Similarly, it is also clear that the economic batch quantity decreases as the cost per piece and inventory carrying rate increase. Set-up cost = $20 per set-up, Annual requirements = 1000, Inventory carrying cost = 10% of value/year, Cost per part = $2 In this example, the factor d/p is ignored. EBQ=\sqrt{ \frac{ 2\times1000\times20 }{2\times0.1} }=447 \text{ parts} Therefore, the number of batches to be made for manufacturing the parts are 1000/447 = 2.24. Nearest, 2 batches can be made and therefore the modified EBQ = 1000/2 = 500 parts. This rounding off only makes sense if we produce the item during exactly one year, and we do not carry over stock from one year to the next.
Text derived from https://en.wikipedia.org/w/index.php?oldid=1371627711 under CC BY-SA 4.0; modifications have been made.