Elwha Dam

The Elwha Dam was a 108-ft (33 m) high dam located in the United States, in the state of Washington, on the Elwha River approximately upstream from the mouth of the river on the Strait of Juan de Fuca.

Uses your system voice; voice and rate in settings.

Snapshot

≈ 5 min read

Names in other languages

No names in other languages are held for this entry yet.

Article bodies are English and are not machine-translated. A name in another language is not a translation of the article.

The Elwha Dam was a 108-ft (33 m) high dam located in the United States, in the state of Washington, on the Elwha River approximately upstream from the mouth of the river on the Strait of Juan de Fuca. The Elwha River Ecosystem and Fisheries Restoration Act of 1992 authorized the US Federal Government to acquire the Elwha Dam and Glines Canyon Dam hydroelectric power projects for decommissioning and demolition for habitat restoration.

Removal of the Elwha Dam began in September 2011 and was fully complete by March 2012, allowing the Elwha River to flow freely through the site.

History of the Elwha fishery

At its peak, the Elwha supported spawning runs of Chinook, coho, chum, pink, and sockeye salmon as well as steelhead, cutthroat, and bull trout. The Chinook were known to reach sizes of 45 kg. Sockeye, Chinook, chum, and pink salmon were all endangered in the Elwha.

Leaving one or both of the dams in place, even with modern fish passage systems, would not result in a dramatic recovery of species due to other factors like water temperature and gravel beds, which would still have negative effects on the fish species (see Table 1). The most valuable spawning habitats are located far upstream from the Glines Canyon Dam, so it still acted as a major barrier to the recovery of the runs.

Removal of both dams was thus considered the only viable option for full restoration of the river and habitat.

Dam removal

The Elwha River Ecosystem and Fisheries Restoration Act of 1992 created funding and government support for mitigation of the dams on the Elwha. While fish ladders were proposed as a possibility, they were ultimately ruled out for the reasons given in the previous section.

The major problem raised with regard to removal of the two dams was the approximately 34 million cubic yards of sediment that had built up behind the dams. Of that 34 million, 28 million was behind the Glines Canyon Dam, while 6 million was behind the Elwha Dam.

Releasing all of this sediment at once would have had devastating effects on the remaining habitats downstream from the dams, as well as along beaches at the coast. A drawdown experiment was conducted on the Glines Canyon Dam to assess the erosion of the sediments from Lake Mills. The lake was drawn down over one week and then allowed to remain stable for one more week.

This test showed that the river would rapidly cut into the existing delta as soon as the lake level dropped, creating a deep, narrow channel. A new delta immediately began to form at the new lake level. Once the lake level was held steady, the channel migrated laterally along the existing delta.

This test resulted in a sediment erosion model in which gradual drawdown of the lake would result in a greatly decreased sediment load downstream. Using this model, the plan was to drain the lake gradually over a two-year time period, allowing much of the sediment to remain in the old lake basin.

The model showed that after the two year dam removal period, the river would begin to restore itself to natural conditions. Sediment discharge rates would increase, resulting in restored and rejuvenated habitats downstream from the dams. Fish were anticipated to return to the upper reaches of the Elwha as soon as a year after dam removal was complete.

While the river might never return to historically large runs, after 15–20 years or more, there should be a recovery of salmon runs to some sort of "pre-dam" condition. In addition to restoring the fish habitats, the draining of Lake Mills and Lake Aldwell would create an additional of terrestrial vegetation, improving elk habitats (Figure 1).

Increased sediment loads were also predicted to help restore the retreating delta at the mouth of the Elwha. Removal of the dams on the Elwha River was a long process. Physical removal started on September 27, 2011, and was completed August 26, 2014.

There is uncertainty about how the river will transform itself and what period of time will be involved. Because so few dam removal projects have been accompanied by scientific study, perhaps fewer than 20, this project will be a model of the effectiveness of dam removal on this scale.

If restoration of the river is successful, it could encourage a movement towards the restoration of natural stream morphology through the removal of larger dams. Most fish populations are expected to make a return to the river (Table 1).

While fish may return to the river as soon as a year after the removal is complete, it may take 15 to 20 years for the river to fully return to its pre-dam conditions. The ultimate goal of the dam removal is restoring the river to a nearly pristine state.

File:Elwha Dam under deconstruction.jpg|September 17, 2011 File:Elwha dam remnants.JPG|February 14, 2012 File:ElwhaDam Finished May2013.JPG|May 23, 2013

See also

Glines Canyon Dam Dam removal

References

Proceedings of the Seventh Federal interagency sedimentation conference. United States (USA):2001.

Elwha River Ecosystem and Fisheries Restoration Act of 1992 Elwha River Restoration – National Park Service Webcam and time lapse animation of dam removal project Elwha Dam Removal Animation Historic American Engineering Record (HAER) documentation, filed under Port Angeles, Clallam County, WA: Undamming the Elwha Documentary produced by KCTS-TV

Text derived from https://en.wikipedia.org/w/index.php?oldid=1373126211 under CC BY-SA 4.0; modifications have been made.