The Hamilton LRT (sometimes known as the B-Line LRT) is a planned light rail line in Hamilton, Ontario, Canada, to operate along Main Street, King Street, and Queenston Road. It is one of six rapid transit lines which form Hamilton's planned HSR Next network. The , 17-stop route is planned to extend from McMaster University to Eastgate Square via downtown Hamilton.

The LRT was originally funded by the province of Ontario in 2015 and in 2018 Infrastructure Ontario issued a request for proposals to design and construct the project. However, in December 2019 the province cancelled procurement citing rising costs.

In May 2021, the project received funding from the provincial and federal governments allowing to project to advance to procurement and construction. Enabling works including utility relations began in 2024 and a request for proposals for the main civil works was issued in May 2025.

The Hamilton LRT (sometimes known as the B-Line LRT) is a planned light rail line in Hamilton, Ontario, Canada, to operate along Main Street, King Street, and Queenston Road. It is one of six rapid transit lines which form Hamilton's planned HSR Next network. The , 17-stop route is planned to extend from McMaster University to Eastgate Square via downtown Hamilton.

The LRT was originally funded by the province of Ontario in 2015 and in 2018 Infrastructure Ontario issued a request for proposals to design and construct the project. However, in December 2019 the province cancelled procurement citing rising costs.

In May 2021, the project received funding from the provincial and federal governments allowing to project to advance to procurement and construction. Enabling works including utility relations began in 2024 and a request for proposals for the main civil works was issued in May 2025.

Planning and funding (2011–2017)

A benefits case analysis was conducted, showing a net benefit for implementing LRT, and that it would be adequate dealing with long-term travel demand growth. An environmental project report was completed in October 2011.

On May 26, 2015, the Government of Ontario announced a shorter route between McMaster University and Queenston Circle, but also including a segment of the A-Line to provide a direct connection to West Harbour GO Station, as well as a pedestrian corridor to the Hamilton GO Centre. The capital costs for the project would be $1 billion, funded entirely by the province.

For the B-Line LRT, procurement was expected to begin in 2017 and line construction in 2019. The transit line was scheduled to open to the public in 2024. On February 2, 2017, the province scrapped the A-Line spur altogether, announcing it would opt for bus rapid transit along the entire A-Line corridor from Hamilton's waterfront to the airport.

On March 28, 2017, Hamilton City Council chose to delay the crucial Environmental Assessment vote to April 19, 2017, citing they needed more time to read it for themselves. On April 19, 2017, City Council voted again to delay the Environmental Assessment, this time to April 26, 2017, claiming the plan at that stage (which was to build Phase 1 from McMaster University to Queenston traffic circle) was indefensible and unfit as it did not go from a destination location to a destination location.

On April 26, 2017, the province announced with the money saved from removing the spur line from King and James to the West Harbour GO Station, they would work with the city to get the Eastgate Square extension included in the capital funding. Later that evening City Council voted to submit the original Environmental Assessment from October 2011 which covers the original route from McMaster University to Eastgate Square.

The motion to submit the original Environmental Assessment was by Terry Whitehead, who was one of the project's harshest critics. The motion passed 10–5, with Councillor Robert Pasuta absent. On August 4, 2017, the Ontario Ministry of the Environment and Climate Change approved the Environmental Project Report (EPR) Addendum for Hamilton's Light Rail Transit (LRT) plan.

Hamilton LRT Project, Metrolinx project site Hamilton Light Rail Transit, City of Hamilton Metrolinx scheme plans BCA Consultation boards Hamilton Light Rail - Site for an advocacy group

Text derived from https://en.wikipedia.org/w/index.php?oldid=1365589676 under CC BY-SA 4.0; modifications have been made.

Sources cited in this revision

34 named source(s) extracted from the cited revision. A source with no author is shown by its publication; nothing is invented.