Hammersmith Bridge is a suspension bridge that crosses the River Thames in west London. It links the southern part of Hammersmith in the London Borough of Hammersmith and Fulham, on the north side of the river, with Barnes in the London Borough of Richmond upon Thames, on the south side of the river.
The current bridge, which is Grade II* listed and was designed by civil engineer Sir Joseph Bazalgette, is the second permanent bridge on the site, and has been attacked three times by the IRA. The bridge was closed indefinitely to all motor traffic in April 2019 after cracks were discovered in the bridge's pedestals.
The closure was extended to pedestrians and cyclists between August 2020 and July 2021 when limited use resumed. Further work and intermittent closures continued until April 2025, when the resurfaced wooden roadway was reopened to pedestrians and cyclists.
Hammersmith Bridge is a suspension bridge that crosses the River Thames in west London. It links the southern part of Hammersmith in the London Borough of Hammersmith and Fulham, on the north side of the river, with Barnes in the London Borough of Richmond upon Thames, on the south side of the river.
The current bridge, which is Grade II* listed and was designed by civil engineer Sir Joseph Bazalgette, is the second permanent bridge on the site, and has been attacked three times by the IRA. The bridge was closed indefinitely to all motor traffic in April 2019 after cracks were discovered in the bridge's pedestals.
The closure was extended to pedestrians and cyclists between August 2020 and July 2021 when limited use resumed. Further work and intermittent closures continued until April 2025, when the resurfaced wooden roadway was reopened to pedestrians and cyclists.
Origins
A group of local people proposed a new bridge at Hammersmith rather than detouring to either Kew Bridge or Putney Bridge to cross the river. The construction of the bridge was first sanctioned by an act of Parliament, the (5 Geo. 4. c.cxii), on 9 June 1824, which established the Hammersmith Bridge Company.
Work began on site the following year, and the bridge was opened on 6 October 1827. Construction of the bridge cost some £80,000 (equivalent to £ million in ). showing the then Hammersmith Bridge densely overloaded by 12,000 spectators watching the University Boat Race, circa 1870.
By the 1870s, the bridge was no longer strong enough to support the weight of heavy traffic and the owners were alarmed in 1870 when 11,000 to 12,000 people crowded onto the bridge to watch the University Boat Race, which passes underneath just before the halfway point of its course. It was the first suspension bridge over the River Thames and was designed by William Tierney Clark.
A further act of Parliament, the (9 Geo. 4. c. lii) was obtained in 1828. The acts also included powers to acquire land by compulsory purchase in order to build approach roads, and required the company to purchase the entire Barn Elms estate (the surplus land was subsequently sold).
The bridge had a clear water-way of . Its suspension towers were above the level of the roadway, where they were thick. The roadway was slightly curved upwards, above high water, and the extreme length from the back of the piers on shore was , supporting of roadway.
There were eight chains, composed of wrought-iron bars, each five inches deep and one thick. Four of these had six bars in each chain; and four had only three, making thirty-six bars, which form a dip in the centre of about . From these, vertical rods were suspended, which supported the roadway, formed of strong timbers covered with granite.
The width of the carriageway was , with two footways of . The chains passed over the suspension towers, and were secured to the piers on each shore. The suspension towers were built of stone, and designed as archways of the Tuscan order.
The approaches were provided with octagonal lodges, or toll-houses, with appropriate lamps and parapet walls, terminating with stone pillars, surmounted with ornamental caps. To increase profits, the company built a floating steamboat pier to the downstream side of the suspension pier closest to Barnes.
The Metropolitan Board of Works purchased the bridge from the Hammersmith Bridge Company in 1880 under the Metropolis Toll Bridges Act 1877 (40 & 41 Vict. c. xcix), and transferred the approach roads to the local authorities (Fulham District Board of Works and the Parish of Barnes). The tolls were removed from the bridge on 26 June 1880.
There were no immediate plans to replace the bridge, which remained sound, until a boat collided with it in 1882 causing damage, and leading to the Metropolitan Board of Works (Bridges, &c.) Act 1883 that authorised the construction of a replacement. In 1884 a temporary bridge was put up to allow a more limited cross-river traffic while a replacement was constructed.
File:Hammersmith Bridge 1, London, UK - April 2012.jpg|Hammersmith Bridge and riverside, seen from the Hammersmith bank File:hammersmith.bridge.arp.jpg|Hammersmith Bridge, seen from the Westminster to Kew tourist boat File:HORR 05.jpg|Rowing crews racing under Hammersmith Bridge File:Hammersmith Bridge, London 12.JPG|End details File:Hammersmith Bridge, London 08.JPG|Tower
Partial reopenings
On 1 June 2021, TfL, Hammersmith and Fulham Council and central government came to a cost-sharing agreement that would reopen the bridge in the near future. The following month, council leader Stephen Cowan announced that the bridge would partially re-open to pedestrians and cyclists from 17 July 2021.
For the first phase, a £6 million, 46-week stabilisation plan designed by consultants Mott MacDonald was approved by the council in August 2021. A second phase, involving extensive strengthening and full restoration, was to allow the bridge to reopen to motor vehicles.
File:Hammersmith Bridge footings repair works.jpg|Repair works to the bridge footings File:Hammersmith Bridge footing cooled in heatwave.jpg|Footing foil-wrapped and cooled in heatwave, with sensors In February 2022, highways contractor FM Conway started work on a 10-month first phase of the restoration. The council approved the full £8.9 million cost, hoping that DfT and TfL would reimburse them for their one-third shares.
Completion of this work was delayed a year as steel became hard to procure due to the Russian invasion of Ukraine. In July 2022, the chains were wrapped in foil and cooled with air-conditioning to 13°C during a heatwave to prevent further cracking.
In October 2022, Hammersmith and Fulham Council agreed to lodge a planning application to temporarily double-deck the bridge to speed up its restoration. The council intended to appoint a private sector contractor to design, renovate, finance and maintain the bridge, with the council's construction and ongoing operation and maintenance costs funded by tolls.
In February 2024, Hammersmith & Fulham Council reopened the central vehicle lane to cyclists for 10 weeks from 13 February 2024, while construction was paused to allow the repair of a steel gantry damaged in a collision with a boat, MV Emerald of London, in December 2023. The last stage was to replace the mechanical bearings on the four corner pedestals of the bridge, after which the council would "review e-mobility options to shuttle residents across the bridge, notably the elderly or disabled".
In January 2024, the cost of repairing the bridge had increased to £250 million (US$316 million). A day later, London Mayor Sadiq Khan said that "I do want that bridge fit for purpose for vehicles" but neither Hammersmith & Fulham Council nor TfL had the money to make it so. TfL's 2024 Business Plan did not include funding for the bridge.
After work on the hangers that link the bridge deck to its suspension chains, the roadway was resurfaced. Its deck is of plywood boards, bolted to timber supports; worn boards and some of the timbers were replaced, at a cost of £2.9 million. The bridge reopened to pedestrians and cyclists in April 2025, with the roadway divided into wide pedestrian and cycle lanes.
Pedestrians can also use the two outer footways. File:Hammersmith Bridge 2024 reopened as cycleway.jpg|February 2024: worn roadway reopened as cycleway File:Hammersmith Bridge 2025 roadway opened to pedestrians and cyclists.jpg|April 2025: resurfaced roadway opened to pedestrians and cyclists On 1 July 2026, Hammersmith and Fulham council shelved its plans to reopen the bridge for motor traffic, because of the extensive repairs needed.
See also
Crossings of the River Thames Sir John Scott Lillie – shareholder in the 1820s Hammersmith Bridge project List of bridges in London
References
Citations Sources
External links
London Transport Museum Photographic Archive London Landscape TV episode (6 mins) about Hammersmith Bridge Information and updates about the 2019 closure of Hammersmith Bridge, and proposals to keep it car-free BHELT (Barnes Hammersmith Electric Light Transit) - A proposal to use self driving pods to carry people across the bridge
Text derived from https://en.wikipedia.org/w/index.php?oldid=1369101051 under CC BY-SA 4.0; modifications have been made.