The Kai Tak Development ( ), abbreviated as "KTD" and formerly called South East Kowloon Development ( ), refers to the redevelopment of the former Kai Tak Airport site in Kai Tak, Kowloon, Hong Kong. After the airport relocated to Chek Lap Kok in 1998, the Hong Kong Government planned for urban development on the old airport site. The plan calls for a multi-purpose sports complex, a metro park, the Kai Tak Cruise Terminal, a hotel, a housing estate, and commercial and entertainment construction projects over an area of more than .
The plan also covered nearby development in areas including Ma Tau Wai, Kowloon City, San Po Kong, Kowloon Bay and Kwun Tong. The planned population is 86,000 people1, accommodated in 30,000 housing units, including 13,000 constructed as part of public housing estates. The total gross floor area is over with over of open space. The total cost for the development is about HK$100 billion.
After several years of planning and discussion, and the decision of a judicial review on Central and Wan Chai Reclamation, the Hong Kong government restarted KTD review and planning in 2004. The Executive Council passed the revised development plan and restarted the project. According to the development plan, the first stage projects were to be finished in or before 2013.…
The Kai Tak Development ( ), abbreviated as "KTD" and formerly called South East Kowloon Development ( ), refers to the redevelopment of the former Kai Tak Airport site in Kai Tak, Kowloon, Hong Kong. After the airport relocated to Chek Lap Kok in 1998, the Hong Kong Government planned for urban development on the old airport site. The plan calls for a multi-purpose sports complex, a metro park, the Kai Tak Cruise Terminal, a hotel, a housing estate, and commercial and entertainment construction projects over an area of more than .
The plan also covered nearby development in areas including Ma Tau Wai, Kowloon City, San Po Kong, Kowloon Bay and Kwun Tong. The planned population is 86,000 people, accommodated in 30,000 housing units, including 13,000 constructed as part of public housing estates. The total gross floor area is over with over of open space. The total cost for the development is about HK$100 billion.
After several years of planning and discussion, and the decision of a judicial review on Central and Wan Chai Reclamation, the Hong Kong government restarted KTD review and planning in 2004. The Executive Council passed the revised development plan and restarted the project. According to the development plan, the first stage projects were to be finished in or before 2013. The second stage projects were to be finished in or before 2016, and the final stage projects were to be completed in or before 2025.
History
1980s
The Hong Kong colonial government commissioned the "Study on Harbour Reclamations and Urban Growth" ( ) in October 1983. It was a study for a proposed plan to address the urban development of Hong Kong. The government worked on the "Metroplan Selected Strategy" study ( ) between 1987 and 1990. Its purpose was to provide a wide-ranging plan for urban renewal-focused land-use, transport and environmental planning. The studied areas included West Kowloon, Kai Tak and other regions. The study was passed by the Executive Council on 17 September 1991. Afterwards, related government departments implemented the strategy according to the study.
1990s
In 1998, the Planning Department undertook several studies on East Kowloon development. After several modifications, the land reclamation plan and the population plan were altered considerably.
2000s
Proposed development timeline
. The first stage infrastructure projects are mostly completed and open. These are the first stage projects: Trade and Industry Tower (completed in 2015) Kai Tak Fire Station (completed) Kai Tak Cruise Terminal building and first berth (completed) Kwun Tong Promenade (completed) Kai Tak Runway Park (completed) District Cooling System (first phase) (completed) Kai Ching Estate Tak Long Estate The second stage infrastructure projects were expected to completed after 2016.
These are the second stage projects: Kai Tak Cruise Terminal: second berth, helicopter landing zone and Tourist Centre (complete September 2014) MTR Tuen Ma line Kai Tak station (construction began 2012, completed in 2020) Route 6 (Central Kowloon Route and Trunk Road T2) (under construction) Underground street to Kowloon City and San Po Kong Kai Tak River (Finished) District Cooling System (second phase) Hospital: Hong Kong Children's Hospital (construction began in 2014, completed in 2017) and Centre of Excellence in Neuroscience Kai Tak Sky Garden, a massive elevated garden, opened in May 2021.
It occupies part of the former runway and apron. Several private residential developments including: Oasis Kai Tak One Kai Tak Vibe Centro Victoria Skye The final stage infrastructure projects are expected to completed after 2024. These are the final stage projects: Kai Tak Sports Park (expected to be completed by 2025) Environmentally Friendly Linkage System (EFLS) (Put on hold) Metro Park Remaining residential and commercial land at north apron commercial land at south apron District Cooling System (third phase)
Transport
MTR Tuen Ma line
The Tuen Ma line involves construction of two stations within the KTD: Kai Tak station and Sung Wong Toi station.
Environmentally Friendly Linkage System
The Environmentally Friendly Linkage System (EFLS) is a monorail transportation system with 12 stations proposed by the government. It will cost around 1.2 billion Hong Kong dollars. The estimated passenger count is up to 200,000 in 2031. The system will account for 15 percent of the public transportation in the Kowloon East Development. The EFLS project is now headed by the Development Bureau with public consultation carried out by the Civil Engineering and Development Department. Construction was predicted to start in 2018 and to be completed in 2023, but was put on hold indefinitely. There is opposition to the monorail system and other proposing a tram system (using ground-level power supply) as a more feasible alternative.
Highway and roads
Hong Kong's Route 6 is proposed to cross the KTD area, using the Central Kowloon Route, Trunk Road T2 and Tseung Kwan O–Lam Tin Tunnel. It will connect West Kowloon, Kowloon East and Tseung Kwan O.
Notes
References
External links
Kai Tak Development, Kai Tak Office, Civil Engineering and Development Department. Kai Tak Development,30 January 2013 ( ). Civil Engineering and Development Department (PDF).
Text derived from https://en.wikipedia.org/w/index.php?oldid=1374448123 under CC BY-SA 4.0; modifications have been made.