Putnam model

The Putnam model is an empirical software effort estimation model created by Lawrence H.[src] Putnam in 1978.[src] Measurements of a software project is collected (e.g., effort in man-years, elapsed time, and lines of code) and an equation fitted to the data using regression analysis.[src] Future effort estimates are made by providing size and calculating the associated effort using the equation which fit the original data (usually with some error).[src] SLIM (Software LIfecycle Management) is the name given by Putnam to the proprietary suite of tools his company QSM, Inc.[src] developed, based on his model.[src] It is one of the earliest of these types of models developed.[src] Closely related software parametric models are Constructive Cost Model (COCOMO), Parametric Review of Information for Costing and Evaluation – Software (PRICE-S), and Software Evaluation and Estimation of Resources – Software Estimating Model (SEER-SEM).[src] A claimed advantage to this model is the simplicity of calibration.[src]

The Putnam model is an empirical software effort estimation model created by Lawrence H.[src] Putnam in 1978.[src] Measurements of a software project is collected (e.g., effort in man-years, elapsed time, and lines of code) and an equation fitted to the data using regression analysis.[src] Future effort estimates are made by providing size and calculating the associated effort using the equation which fit the original data (usually with some error).[src] SLIM (Software LIfecycle Management) is the name given by Putnam to the proprietary suite of tools his company QSM, Inc.[src] developed, based on his model.[src] It is one of the earliest of these types of models developed.[src] Closely related software parametric models are Constructive Cost Model (COCOMO), Parametric Review of Information for Costing and Evaluation – Software (PRICE-S), and Software Evaluation and Estimation of Resources – Software Estimating Model (SEER-SEM).[src] A claimed advantage to this model is the simplicity of calibration.[src] ==The software equation== While managing R&D projects for the Army and later at GE, Putnam noticed software staffing profiles followed the Rayleigh distribution.[src] Putnam used his observations about productivity levels to derive the software equation: \frac {B^{1/3} \cdot \text{Size}}{ \text{Productivity} } = \text{Effort}^{1/3} \cdot \text{Time}^{4/3} where: Size is the product size (whatever size estimate is used by your organization is appropriate).[src] Putnam uses ESLOC (Effective Source Lines of Code) throughout his books.[src] B is a scaling factor and is a function of the project size.[src] Productivity is the Process Productivity, the ability of a particular software organization to produce software of a given size at a particular defect rate.[src] Effort is the total effort applied to the project in person-years.[src] Time is the total schedule of the project in years.[src] In practical use, when making an estimate for a software task the software equation is solved for effort: \text{Effort} = \left[ \frac {\text{Size}} {\text{Productivity} \cdot \text{Time}^{4/3}}\right]^3 \cdot B An estimated software size at project completion and organizational process productivity is used.[src] Plotting effort as a function of time yields the Time-Effort Curve.[src] The points along the curve represent the estimated total effort to complete the project at some time.[src] One of the distinguishing features of the Putnam model is that total effort decreases as the time to complete the project is extended.[src] This is normally represented in other parametric models with a schedule relaxation parameter.[src] This estimating method is fairly sensitive to uncertainty in both size and process productivity.[src] Putnam advocates obtaining process productivity by calibration: \text{Process Productivity} = \frac {\text{Size}} { \left[ \frac {\text{Effort}}{B} \right]^{1/3} \cdot \text{Time}^{4/3} } Putnam makes a sharp distinction between 'conventional productivity' : size / effort and process productivity.[src] ==External links== QSM, Inc.[src]

33 sentences · 33 cited inline · 0 references stored

References

No reference rows published for this article.

Cite this article

MLA

"Putnam model." encyclopegia.org, 2024, https://encyclopegia.org/wiki/putnam-model. Accessed 27 November 2026.

Chicago

"Putnam model." encyclopegia.org. Accessed November 27, 2026. https://encyclopegia.org/wiki/putnam-model.

APA

encyclopegia.org. (2024). Putnam model. Retrieved November 27, 2026, from https://encyclopegia.org/wiki/putnam-model

Accessed November 27, 2026 · CC BY-SA 4.0 · citation page · JSON

Related articles

Top Model O Reality

stub · references available

Top Model of the World

stub · references available

Breda Model 35

stub · references available

Skoda 305 mm Model 1911 howitzer

stub · references available

Lebel Model 1886 rifle

stub · references available

Springfield Model 1866

stub · references available

animal model

stub · references available

actor model

stub · references available
CC BY-SA 4.0 · share-alike · https://en.wikipedia.org/w/index.php?oldid=1258308802 · 0.5 · snapshot enwiki-001258308802

Cite · JSON · Search

Related services and records

Services

  • Estate — measured countries, lanes and facts
  • Intel — live corroborated events
  • Legal — statutes, cases and citations
  • Encyclopedia — articles with inline sources
  • Space — launches, satellites and orbits
  • Search — federated search and reports
  • Pass — passport account and SSO
  • Corpora — read-only corpus origins
  • e01 — self-hosted corpora and tools
  • Careers — open roles: frontier engineers and sales partners

Text and metadata only; each target carries its own sources. Missing data is published as no-data, never estimated.