A9 dualling project

Uses your system voice; voice and rate in settings.

Snapshot

≈ 7 min read

Names in other languages

No names in other languages are held for this entry yet.

Article bodies are English and are not machine-translated. A name in another language is not a translation of the article.

The A9 dualling project is an ongoing infrastructure project in Scotland to upgrade the A9 between Perth and Inverness from a single carriageway to a dual carriageway. A dual carriageway allows drivers to overtake safely, as they do not have to meet oncoming traffic; and the crash barriers on the central reservation greatly reduce the frequency of head-on collisions.

As most of the A9 is currently a single carriageway, drivers may have to overtake heavy goods vehicles (HGVs) and other slow-moving vehicles as they are limited to , lower than the speed limit for cars and motorcycles. The A9 has been dubbed Scotland's most dangerous road. In 2022, there were 17 fatalities, its highest level in 20 years before falling to four in 2023.

The project was announced in 2011 in response to the safety concerns with overtaking and head-on collisions. Construction started in 2015 starting with a section between Kincraig and Dalraddy (near Aviemore) followed by the Luncarty to Pass of Birnam in 2019.

This project was originally due to finish in 2025, but has since been delayed to 2035. , two out of eleven sections have been completed, totalling 11 miles (17 km), leaving 77 miles (124 km) to be upgraded. The sections between Tomatin and Moy, as well as between Tay Crossing and Ballinluig are under construction as of November 2025. Both sections are due to be finished in 2028.

The A9 dualling project is an ongoing infrastructure project in Scotland to upgrade the A9 between Perth and Inverness from a single carriageway to a dual carriageway. A dual carriageway allows drivers to overtake safely, as they do not have to meet oncoming traffic; and the crash barriers on the central reservation greatly reduce the frequency of head-on collisions.

As most of the A9 is currently a single carriageway, drivers may have to overtake heavy goods vehicles (HGVs) and other slow-moving vehicles as they are limited to , lower than the speed limit for cars and motorcycles. The A9 has been dubbed Scotland's most dangerous road. In 2022, there were 17 fatalities, its highest level in 20 years before falling to four in 2023.

The project was announced in 2011 in response to the safety concerns with overtaking and head-on collisions. Construction started in 2015 starting with a section between Kincraig and Dalraddy (near Aviemore) followed by the Luncarty to Pass of Birnam in 2019.

This project was originally due to finish in 2025, but has since been delayed to 2035. , two out of eleven sections have been completed, totalling 11 miles (17 km), leaving 77 miles (124 km) to be upgraded. The sections between Tomatin and Moy, as well as between Tay Crossing and Ballinluig are under construction as of November 2025. Both sections are due to be finished in 2028.

Early upgrades

The 110 mile (176 km) section of the A9 between Perth and Inverness was substantially rebuilt between 1972 and 1986. The rebuilt road follows essentially the same route as before except where it bypasses towns and villages instead of running through their centres.

At the time of the rebuild, traffic levels were low enough to not warrant a dual carriageway, although provision was given should it be needed. Parts of the road were upgraded to dual carriageway where there are steep gradients or where traffic flows are expected to be high.

The most significant alteration of the A9 route was the realignment of the route north from Inverness, crossing the Moray Firth via the Kessock Bridge, cutting through the Black Isle and back across the Cromarty Firth. This shortened the route by , bypassing Beauly, Muir of Ord and Dingwall.

Construction of the Kessock Bridge began in 1976, and was completed in 1982. between Dalnacardoch and Dalnaspidal Between Perth and Inverness, the road has been dubbed Killer A9, because of accidents and fatalities where dual-carriageway sections merge into a single carriageway; the principal cause is that motorists drive at excessive speeds to overtake lines of slower-moving vehicles before the dual carriageway ends. Dangerous overtaking manoeuvres on long single-carriageway stretches of the road are also common causes of accidents.

Delays

The construction project started in September 2015, and was originally scheduled for completion in 2025, but in February 2023, the Scottish Government reported that the original deadline was "unachievable". A review from the BBC stated that the civil engineers knew that finishing the project by its original deadline of 2025 was going to be impossible.

In December 2023, Transport Scotland announced that this deadline was postponed to late 2035 and announced a new delivery plan. Former first minister of Scotland Nicola Sturgeon stated that the reason for the delay was because it "faced significant challenges beyond their control, including from Brexit and the Covid pandemic" She apologised that the 2025 deadline could not be met.

She denied that the Scottish National Party (SNP) or the Scottish Government "messed up". Other factors included the Russian invasion of Ukraine.

These claims were not well received by residents at the northern end of the A9, and it was pointed out that issues such as Brexit, the COVID-19 pandemic and the war in Ukraine were not factors when the project started to slow down, with former First Minister Alex Salmond believing the project became less of a priority after he left the Scottish Government in 2014. The first two sections of the scheme were already delayed by no more than a couple of months.

Only 11 out of 90 miles of the A9 were converted to dual carriageway from 2015 to 2023, leaving 79 miles to be dualled. According to a 2012 report, Alex Neil, Cabinet Secretary for Infrastructure and Capital Investment, said that the "2025 [deadline] was challenging but achievable" In September 2023, Fergus Ewing was suspended by the SNP, in part for criticising the party for the A9 dualling delays.

In March 2024, Ewing, a longstanding MSP, and former minister in the Scottish Government, issued a public letter to Transport Secretary Fiona Hyslop highlighting delays to the project and continuing fatalities on the road. In November 2024, the SNP announced it was considering slashing the national speed limit on single carriageway roads nationwide from 60 mph to 50 mph, causing major concern from campaigners that it would further push back dualling of the A9, or lead to the project being cancelled outright, and that a further reduced speed limit would only increase frustration and lead to more accidents.

The consultation to reduce the national speed limit on single carriageways from 60 to 50 mph was rejected on 15 December 2025, after over 77% of the 19,500 responses objected to the reduced speed limit. On the other hand, proposals to increase the HGV speed limit on single carriageways to 50 mph (to align with England and Wales plus the A9 between Perth and Inverness) have been approved.

There were calls to accelerate the dualling programme and to prioritise upgrading the deadliest sections of single carriageway. This was rejected by the Scottish Government in January 2025, which risks the project to miss its already-delayed deadline of 2035.

Transport Scotland reported that in order to meet the 2035 deadline, there could be up to 43 miles (70 km) of concurrent roadworks on the A9. Each section of roadworks will be limited to 15 miles (24 km).

Text derived from https://en.wikipedia.org/w/index.php?oldid=1351750152 under CC BY-SA 4.0; modifications have been made.