Nemo Link is a 1,000 MW HVDC submarine power cable between Richborough Energy Park in Kent, the United Kingdom and Zeebrugge, Belgium. The project is a joint venture between British National Grid and Belgian Elia. The 400 kV electrical interconnector is the first between the two countries, with an annual transmission capacity of 8.76 TWh . The link has been fully operational since 31 January 2019, and has transported 29 TWh during its first 5 years; 24.75 TWh to the UK and 4.25 to Belgium with an availability above 99%.
Nemo Link is a 1,000 MW HVDC submarine power cable between Richborough Energy Park in Kent, the United Kingdom and Zeebrugge, Belgium. The project is a joint venture between British National Grid and Belgian Elia. The 400 kV electrical interconnector is the first between the two countries, with an annual transmission capacity of 8.76 TWh . The link has been fully operational since 31 January 2019, and has transported 29 TWh during its first 5 years; 24.75 TWh to the UK and 4.25 to Belgium with an availability above 99%.
History
In 2015, contracts totalling €500 million were awarded to Siemens for the construction of the two onshore HVDC converter stations and to J-Power Systems Corporation for the cable system. The contract for the laying of the actual cable was awarded to DeepOcean who completed the work in 2017 and 2018.
See also
HVDC Cross-Channel, 2,000 MW between UK and France BritNed, 1,000 MW between UK and the Netherlands
References
External links
4c page
Text derived from https://en.wikipedia.org/w/index.php?oldid=1373455923 under CC BY-SA 4.0; modifications have been made.